Commissioning runs and technical missions on NIRPS.
Run | Date | Activities |
---|---|---|
Commissioning 1 | 29 Nov.-6 Dec. 2019 | Front end installation + HARPS recommissioning |
Commissioning 2 | 8-17 June 2021 | AO+guiding tests |
Commissioning 3 | 22 Sep.-1 Oct. 2021 | AO+guiding+ADC tests |
Commissioning 4 | 26 Nov.-6 Dec. 2021 | Fibre link installation and tests |
Technical activities | Mar.-Apr. 2022 | Back end installation |
First light | 17 May 2022 | First light with the whole instrument |
Commissioning 5 | 7-19 June 2022 | |
Technical activities | Jul.-Aug. 2022 | Replacement of echelle grating |
Commissioning 6 | 19 Sept.-1 Oct. 2022 | |
Technical activities | Oct. 2022 | Blaze angle adjustment + fibre stretchers addition |
Commissioning 7 | 26 Nov.-7 Dec. 2022 | |
Commissioning 8 | 16-27 Jan. 2023 | |
Commissioning 9 | 1-11 Mar. 2023 | |
Start of science operation | 1 April 2023 | |
Technical activities | 12-21 Apr. 2023 | Spectrograph thermal enclosure installation |
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.