Table 6
Main events of the ART-XC flight from launch to the start of the survey.
Date | Time | Event |
---|---|---|
2019/07/13 | 15:31 | Launch |
2019/07/13 | 17:31 | End of s/c acceleration and separation of DM-03 booster from s/c |
2019/07/13 | 18:43 | Telescope subsystems switched on and stores onboard information |
2019/07/13 | 18:58 | Telescope thermal control system switched on |
2019/07/18 | 18:42 | First telemetry from first X-ray camera received |
2019/07/21 | All cameras switched on and reported ‘healthy’ | |
2019/07/22 | First trajectory correction | |
2019/07/23 | 18:31 | Telescope cover opened |
2019/07/27 | First X-ray calibration source opened and first calibration of first camera performed, | |
start of cameras commissioning | ||
2019/07/30 | 17:29 | ‘First Light’ (image of Cen X-3 on all cameras) |
2019/08/06 | Second trajectory correction | |
2019/08/25 | End of seven cameras commissioning, EEPROM of first camera successfully reprogrammed | |
to working configuration, start of ART-XC calibration and performance verification phase | ||
2019/10/05 | End of the ART-XC calibration and performance verification phase | |
2019/10/21 | Third trajectory correction | |
2019/12/12 | Start of the all-sky survey |
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.