SWA-HIS ground calibration programme.
Location | Dates | Configuration | Scope of calibration | |
---|---|---|---|---|
1 | H30 at SwRI | Sep–Oct 2015 and Jan–Mar 2016 | EA-IS | Optimisation of the EA-IS voltages |
2 | H19 at SwRI | Sep–Nov 2016 | Complete sensor minus EA-IS | Mass (1−56) and energy (0.1−450 keV) response |
3 | Mefisto at Bern | Jan–Feb 2017 | Complete sensor | Charge (1−4), mass (1−84) and energy/charge (3−60 keV/e) response |
4 | H19 at SwRI | Mar–Apr 2017 | Complete sensor | Geometric factor |